Dhaka Metro future lines: MRT Line 1, Line 5 North and Line 5 South routes and dates
Dhaka has one metro line today, MRT Line 6. Three more are on the way: MRT Line 1, the country’s first underground metro, from the airport to Kamalapur with a branch to Purbachal (target December 2033); MRT Line 5 North from Hemayetpur to Bhatara through Mirpur, Banani and Gulshan (target December 2032); and MRT Line 5 South from Gabtoli to Dasherkandi (planned, target August 2033). Before any of them, Line 6 itself is getting one more station: Kamalapur, expected in July 2027.
Dhaka Metro network map: today and tomorrow
MRT Line 1: airport to Kamalapur, underground
Line 1 will be Bangladesh’s first underground metro. It is 31.24 km long in two parts: the Airport route, 19.87 km underground from Hazrat Shahjalal International Airport to Kamalapur, and the Purbachal route, 11.36 km mostly elevated from Notun Bazar to Purbachal. Construction is under way, funded by the government and JICA; the target is December 2033(the original target was 2026) and the estimated cost is about ৳1,14,395 crore. On 27 October 2026 contracts were signed for the depot and elevated sections of Line 1 and Line 5 North.
Airport route stations (12)
- Airport
- Airport Terminal 3
- Khilkhet
- Nadda
- Notun Bazar (interchange)
- Uttar Badda
- Badda
- Aftabnagar (interchange)
- Rampura
- Malibagh
- Rajarbagh
- Kamalapur (interchange)
Purbachal route: Notun Bazar, Nadda, then (7 more)
- Joar Sahara
- Boalia
- Mastul
- Purbachal West
- Purbachal Centre
- Purbachal East
- Purbachal Terminal
MRT Line 5 North: Hemayetpur to Bhatara
Line 5 North crosses the city from west to east: about 20 km with 14 stations, from Hemayetpur in Savar through Gabtoli, Mirpur 10, Banani and Gulshan to Bhatara. It meets Line 6 at Mirpur 10 and Line 1 at Notun Bazar. The target is December 2032, at an estimated ৳89,848 crore.
- Hemayetpur
- Baliarpur
- Madhumati
- Amin Bazar
- Gabtoli (interchange)
- Darus Salam
- Mirpur 1
- Mirpur 10 (interchange)
- Mirpur 14
- Kachukhet
- Banani
- Gulshan 2
- Notun Bazar (interchange)
- Bhatara
MRT Line 5 South: Gabtoli to Dasherkandi
Line 5 South is still at the planning and design stage: about 17.3 km, mostly underground, with 15 stations from Gabtoli through Shyamoli, Asad Gate, Karwan Bazar, Hatirjheel and Aftabnagar to Dasherkandi. It is to be funded by the Asian Development Bank and Korea, with a target of August 2033 and an estimated cost of ৳45,503 crore. It was not part of the October 2026 contracts.
- Gabtoli (interchange)
- Technical
- Kallyanpur
- Shyamoli
- College Gate
- Asad Gate
- Shukrabad
- Karwan Bazar (interchange)
- Hatirjheel
- Tejgaon
- Aftabnagar (interchange)
- Aftabnagar Centre
- Aftabnagar East
- Nasirabad
- Dasherkandi
Line 6 to Kamalapur: the next station to open
The first new station riders will actually use is Kamalapur, 1.16 km past Motijheel next to Kamalapur railway station. Civil work was about 85% done at the end of September 2026, and service is expected in July 2027. Fares are already on the official chart: see the Kamalapur station guide.
Where the lines will meet
| Interchange | Lines |
|---|---|
| Mirpur 10 | MRT Line 6, MRT Line 5 North |
| Karwan Bazar | MRT Line 6, MRT Line 5 South |
| Kamalapur | MRT Line 6, MRT Line 1 |
| Notun Bazar | MRT Line 1, MRT Line 5 North |
| Aftabnagar | MRT Line 1, MRT Line 5 South |
| Gabtoli | MRT Line 5 North, MRT Line 5 South |
What about Lines 2 and 4?
Dhaka’s Revised Strategic Transport Plan (2015) maps six metro lines: 1, 2, 4, 5 North, 5 South and 6. Lines 2 and 4 are still long-term plans with no construction, so there is no route or date to rely on yet. We will add them here when DMTCL publishes firm plans.
More: Line 6 route map and stations · Dhaka Metro Rail paragraph for students
Sources
- Wikipedia: MRT Line 1 (Dhaka Metro Rail)
- DTCA: Leaflet for MRT Line 1 and 5 (PDF)
- Prothom Alo: Metro rail extension to Kamalapur 85% complete, service set to begin in July
- Wikipedia: Dhaka Metro Rail (planned lines)
Frequently asked questions
When will MRT Line 1 open?
The target is December 2033. It was first planned for 2026. Line 1 runs underground from the airport to Kamalapur, with an elevated branch from Notun Bazar to Purbachal.
Is MRT Line 1 underground?
Mostly. The 19.87 km Airport–Kamalapur route is underground, making it Bangladesh’s first underground metro. The 11.36 km Purbachal route is mainly elevated.
What is the route of MRT Line 5 North?
Hemayetpur, Baliarpur, Madhumati, Amin Bazar, Gabtoli, Darus Salam, Mirpur 1, Mirpur 10, Mirpur 14, Kachukhet, Banani, Gulshan 2, Notun Bazar and Bhatara: about 20 km and 14 stations, target December 2032.
What is the route of MRT Line 5 South?
Gabtoli to Dasherkandi through Shyamoli, Asad Gate, Karwan Bazar, Hatirjheel and Aftabnagar: about 17.3 km, mostly underground, 15 stations. It is still being planned, with a target of August 2033.
Where can I change between metro lines in Dhaka?
Once the new lines open: Mirpur 10 (Line 6 and 5 North), Karwan Bazar (Line 6 and 5 South), Kamalapur (Line 6 and 1), Notun Bazar (Line 1 and 5 North), Aftabnagar (Line 1 and 5 South) and Gabtoli (5 North and 5 South).
How many metro lines will Dhaka have?
Six are in the long-term plan: Lines 1, 2, 4, 5 North, 5 South and 6. Only Line 6 is open today; Lines 1 and 5 North are under construction and 5 South is in planning.